fbpx ;

PROJECTS OF ALL COMPLIXITY

key projects since 1996

O & M Services

Providing Reliable O&M Services

AUXILARY STEAM BOILER

Complete Boiler Solution For Power Plant.

PREV
NEXT

ROSH POWER PLANT

Project Name: 412 Mw Comb Cycle Plant
Location: Abdul Hakeem
Completion Period:One Year
Time Period:1997-1998
Client: BVI (Black And Vich Inte) And Icc
Contractor: Shr Constructions (Pvt) Ltd
SCOPE OF WORK:
Installation Of Steam Condenser.
Installation of by Pass Exhaust system.
Defuser, Diverter dampers, Silencers and Stack With internal insulation.
Installation of Air intake Duct and Filters

PARCO OIL RE-FINERY

Project Name:Parco Oil Refnery
Location: Mehmood Kot Muzafar Garh
Completion Period: 3 Years
Time Period: 1999-2001
Client: PARCO/DESCON
Contractor: Shr Constructions (Pvt) Ltd
SCOPE OF WORK:
16”Inch Main Firefghting Pipe Line.
Installation & Fabrication Of under ground OWS-WWS.
Fabrication & Erection Of Area Zoo Pip-ing With Pipe Support

ZAMZAMA BHP GAS FIELD

Project Name: Gas Field
Location: Gas Field Dadu Johi
Completion Period: 2 Years
Time Period: 2001-2002
Client: BHP/DESCON
Contractor: Shr Constructions (Pvt) Ltd
SCOPE OF WORK:
Complete Piping Of Dadu Gas Filed EWT
Complete Structure Of Pipe Racks .
Compressor and complete piping
Fabrication & Erection of Condensate Tanks DIA 12m (2No

QADANWARI GAS FIELD

Project Name: Miano Upgradation
Location: Qadanwari Sindh
Completion Period: 1 Year
Time Period: 2001-2002
Client: OMV/ Descon
Contractor: Shr Constructions (Pvt) Ltd
SCOPE OF WORK:
Piping Of Omv Qadanwari Gas Field 140000 Dia Inch.
Fabrication Of Heat Exchanger at OMV.
Erection Of Heat Exchanger 140000 Dia Inch at OMV

SAWAN GAS FIELD

Project Name:Sawan Gas Field
Location: Kadanwari Kathor Sindh Pakistan
Completion Period:One Year
Time Period: 2002-2003
Client: OMV/Descon
Contractor: Shr Constructions (Pvt) Ltd
SCOPE OF WORK:
Complete Erection Of Flyer Line Structure.
Complete Piping Of Flyer & SS 24” Piping Structure = 210 MT Dia Approx 18

PARCO PIPELINE PROJECT

Project Name:Parco White Oil Refinery
Location: Mehmood Kot Qasba Gujrat
Completion Period: 2 Years
Time Period: 2004-2005
Client:PAPCO
Contractor: Shr Constructions (Pvt) Ltd
SCOPE OF WORK:
Fabrication Of Oil Tanks 55 Dia (4 N)
Erection Of Oil Storage Tanks 55 Dia Metre (4 N)

DG CEMENT FACTORY

Project Name: DG Cement Factory
Location: Chakwal Kalar Kahar
Completion Period: 2 Years
Time Period: 2004-2005
Client: DG Cement Factory/EKL
Contractor: Shr Constructions (Pvt) Ltd
SCOPE OF WORK:
Fab & Ere Of Pan Conveyor, Cement Silo.
Erection of Cement Mill Venticat 29 (2 Nos).
Fab & Ere Of bag Filters, Filters, 12 Packing.

PARCO OIL REFINERY

Project Name:Parco Oil refnery
Location: Mehmood Kot Qasba Gujrat
Completion Period: 2 Years
Time Period: 2004-2005
Client:PAPCO
Contractor: Shr Contracting Co
SCOPE OF WORK:
Grubbing, Cutting, Filling, leveling of tank.
Excavation, Back flling and concrete foundations
TOP